Introduction: As part of Construction Engineering, while preparing the instrument cable tray / trench routing as a construction layout the following basic information is required.
#InstrumentCableTrayLayout #InstrumentCableTrenchLayout #TrayLayout
#CableRouting
1) Overall plot plan for marking the details of all equipment Skids and packages are to be installed as per the overall plot plan, as shown in figure shown in this video.
2) Planning can be started for instrumentation construction work, e.g., preparing the cable trench tray routing layout, JB location and instrument locations.
3) The minimum tray/trench routing, elevation and type of cable tray, size of tray and all the detailed sections are generally shown.
4) The construction engineering is done to minimize the time & effort during the construction phase when the actual implementation of approved drawings/ documents is carried out. It minimizes errors such as, mismatching of cable routing, tray/trench work and safety precaution etc.
Note: Keep watching our channel eFunda where we are creating videos related to Engineering and Project Topics and saved under separate play List.
1) Fundamentals
• Magic Word - Inspiring Thoughts
2) Project / Career
• Project / Career
3) Engineering
• Engineering
4) Instrumentation & Control Engineering
• Instrumentation & Control Engineering
5) Historical / Social
• Historical / Social
Please follow us:
eFunda Instagram – / efundachannel
Facebook - https://www.facebook.com/efundachanne...
Please LIKE, SHARE and SUBSCRIBE to our channel eFunda channel .
Regards,
Team eFunda
Watch video Instrument Cable Tray / Trench Layout (Part -12I) online without registration, duration hours minute second in high quality. This video was added by user eFunda Channel 31 December 2021, don't forget to share it with your friends and acquaintances, it has been viewed on our site 15,414 once and liked it 225 people.