Oil and Gas Engineering (Part 2) Wellhead and Wellhead Control Panel (WHCP)

Опубликовано: 22 Май 2021
на канале: eFunda Channel
40,451
801

A Wellhead Platform (WHP) mainly includes an integrated deck, utility systems, wellhead systems, helideck and drilling facilities. At times, it could be linked to Floating, Production, Storage and Offloading (FPSO) vessel or Central Production Platforms (CPP).

The Christmas tree valves shall be actuated by WHCP with hydraulic supply and these valves shall be operated through the WHT ESD system, using electrical solenoid valves. These solenoid valves shall be part of the WHCP and the Shutdown logic shall be executed at the WHT ESD System.

Usually, Wellhead Control Panel (WHCP) is place about 100 meters away from the wellhead or Christmas tree and the Hydraulic or Pneumatic output from panel is connected to wellhead through properly sized tubes.
#Oil and Gas #WHCP # Wellhead #ESD System #SSSV #SCSSV #SSV


Смотрите видео Oil and Gas Engineering (Part 2) Wellhead and Wellhead Control Panel (WHCP) онлайн без регистрации, длительностью часов минут секунд в хорошем качестве. Это видео добавил пользователь eFunda Channel 22 Май 2021, не забудьте поделиться им ссылкой с друзьями и знакомыми, на нашем сайте его посмотрели 40,451 раз и оно понравилось 801 людям.