Elapsed Time vs Duration vs Effort

Опубликовано: 31 Январь 2024
на канале: Pieter Rademeyer
330
12

Theory: Task Dependencies (or task Relationships):    • Task Dependencies (or task Relationsh...  
Theory: Fixed Duration, Fixed Units, Work – effort driven On or OFF:    • Fixed Duration, Fixed Units, Work - e...  
19 TIPS for setting-up the perfect project:    • How to prepare, setup and manage the ...  
   / @pieterrademeyer1   (Visit my Channel for Project Management topics and videos)

In this video project schedule example is used to explain the difference between Elapsed Time, Duration, and Effort (or Work).
Scheduling formula: Work (or Effort) = Duration x Resource Units
Elapsed time = calendar days (incl. weekends and public holidays)
Duration = amount of time required to complete a task (hours, days, weeks)
Units = number of resources assigned to a task (people, equipment, material)
Effort (or Work) = amount of effort required to complete a task (hours, days)


Смотрите видео Elapsed Time vs Duration vs Effort онлайн без регистрации, длительностью часов минут секунд в хорошем качестве. Это видео добавил пользователь Pieter Rademeyer 31 Январь 2024, не забудьте поделиться им ссылкой с друзьями и знакомыми, на нашем сайте его посмотрели 330 раз и оно понравилось 12 людям.